ERP implementation plan

Most ERP plans are right on the day they are written. They stop being right between the meetings: a fit gap sits undecided, a date moves a day at a time, and nobody sees the go live date go until the quarter it was in has gone.

Below is the sequence a package implementation owes, the working days each stage is given before anything is negotiated, and the rules the plan is measured against every morning. It is the real rule set, not an illustration of one.

The stages, and what each one is given

Every program owes these twelve, in this order. The days are working days and they are the starting point the scheduler reasons from, not a quote: a real program moves them, and the point of writing them down is that moving one has to be a decision somebody made.

StageWorking days
Initiateten working days
Discoverfifteen working days
Requirementstwenty working days
Designtwenty working days
Build40 working days
SITfifteen working days
UATfifteen working days
Trainingten working days
Cutover rehearsalfive working days
Go liveone working day
Hypercaretwenty working days
Benefitstwenty working days

A package implementation adds two stages that a build does not have, and both of them are where the scope is actually decided.

StageWorking days
Fit gapfifteen working days
Configuration30 working days

The rules this plan is checked against

These are read out of the engine rather than written here, so the table is what actually runs. Seven rules apply to this kind of program on top of the nineteen every program owes, and all of them are checked against every row, every weekday morning.

RuleKindWhat it means
PK-001OrderFit gap cannot start until Requirements is done.
PK-002OrderDesign cannot start until Fit gap is done.
PK-003OrderConfiguration cannot start until Design is done.
PK-004OrderSIT cannot start until Configuration is done.
PK-005Lead timeFifteen working days must pass between Configuration and Go live.
PK-010EvidenceFit gap cannot close until the evidence is attached: gap decision.
PK-011EvidenceConfiguration cannot close until the evidence is attached: config workbook.

Underneath them sit the nineteen baseline rules every program is held to, whatever it is: design does not complete without sign-off, SIT does not complete without results, go live does not complete without a recorded go/no-go. The documentation has the workbook those rows live in.

RuleKindWhat it means
BR-001OrderDiscover cannot start until Initiate is done.
BR-002OrderRequirements cannot start until Discover is done.
BR-003OrderDesign cannot start until Requirements is done.
BR-004OrderBuild cannot start until Design is done.
BR-005OrderSIT cannot start until Build is done.
BR-006Lead timeThree working days must pass between SIT and UAT.
BR-007Lead timeFive working days must pass between UAT and Training.
BR-008OrderCutover rehearsal cannot start until Training is done.
BR-009Lead timeFive working days must pass between Cutover rehearsal and Go live.
BR-010Lead timeTwo working days must pass between Training and Go live.
BR-011OrderHypercare cannot start until Go live is done.
BR-012Lead timeTwenty working days must pass between Hypercare and Benefits.
BR-020EvidenceDesign cannot close until the evidence is attached: design sign-off.
BR-021EvidenceSIT cannot close until the evidence is attached: test result.
BR-022EvidenceUAT cannot close until the evidence is attached: uat sign-off.
BR-023EvidenceTraining cannot close until the evidence is attached: attendance.
BR-024EvidenceCutover rehearsal cannot close until the evidence is attached: rehearsal report.
BR-025EvidenceGo live cannot close until the evidence is attached: go/no-go decision.
BR-030FreezeNo change goes in inside ten working days of Go live.

Where these plans actually go

  • The gap with no decisionPK-010 will not let fit gap close until every gap has a disposition: configure, customize, process change or accept. An undecided gap has no date of its own, so it never looks late, and it blocks the outcome waiting on it.
  • Configuration still moving at go livePK-005 freezes configuration a set number of working days out. The freeze is not bureaucracy: every change inside it invalidates the test evidence that the go/no-go decision rests on.
  • Training booked before UAT is stableBR-007 holds training until UAT settles, because training people on a build that is still moving means training them twice and trusting the attendance record from the first time.
  • A go live with no go/no-goBR-025 will not close go live without a recorded decision. It is the gate most often waved through, and it is the only record of who agreed to proceed and on what evidence.

Build one and look at it

The demo builds ERP implementation program in front of you from the rules above, then hands you the real screens on the one it just built. There is something genuinely wrong in it on purpose, and it does not tell you what.

Watch it build one, or pick a different kind of program. No card, nothing to install.

Run this on your own program.

Describe it in a sentence and it builds the plan, checks your date against these rules before you commit to it, and asks the owners every weekday after. The first thirty days are free.

Tell me about your program